Environmental director
Band manager, all projects · Scope the whole operating portfolio ·
Signs in on the portal.
Status today: this role cannot be minted at all. The signed session claim
carries project — singular
(workers/esg-query/src/authz.ts:23).
A portfolio reader has no representation.
Scope note. The persona's pre-award remit (bid · budget · mobilisation) is parked — there is no bidding, costing or onboarding activity. This file is operational only. See PERSONA §0.
1. Who this is
Clarke Gunter. Every operating project, not one. Answers to the client, the regulator and the JV board. The difference from the manager is not seniority — it is that the manager asks "how is my site going" and the director asks "where is my exposure, and what have we committed to."
2. Why they open the portal
Six questions, ordered by how fast the answer decays — not by how the system is organised.
| Q | Question | What it holds |
|---|---|---|
| Q1 | Is anything about to hurt me? | overdue NCRs · permits inside 60 days · live criticals · incidents with a regulatory clock running · major audit findings with no NCR · repeat findings |
| Q2 | What needs me personally? | the decision queue, unfiltered by project |
| Q3 | Is the record defensible? | closure by reason · failed-first-fix · self-verified · coverage vs conformity · attestation method · investigation method stated |
| Q4 | Where is it concentrating? | new vs closed · by area · by project · and on the plan |
| Q5 | Is the field reaching me? | undelivered tickets · inspections due vs submitted · last contact per device and inspector |
| Q6 | What is coming? | permits · scheduled inspections and audits · obligations due |
Q1 is the only part allowed to be red. Q5 is the honesty panel — no process completes end to end today, and a portal that does not say so is lying by omission.
3. Screens
| Screen | Purpose | Today |
|---|---|---|
| Portfolio lens | all projects, one page, exposure first | ⚠️ surfaces exist, single-project |
| Decision queue (unfiltered) | portfolio-wide decisions | ⚠️ |
| Incident spine | one page per event: observation → evidence → obligation → decision → action → outcome, with recurrence | ❌ the demo's whole narrative has nowhere to live |
| Integrity panel (Q3) | evidence quality across projects | ⚠️ |
| Release | what has gone to a client, regulator or board, and when | ❌ |
| Spatial view | where it is concentrating, on the plan | ✅ siteMap.tsx, planCanvas.tsx |
4. Features and functionality required
| ID | Feature | What it must do | Today |
|---|---|---|---|
| F-DIR-1 | Multi-project scope in the signed claim | projects: string[]. Without it there is no director. Do it while the pilot is one project and ["p1"] is a trivial migration | ❌ the blocker |
| F-DIR-2 | Portfolio exposure panel (Q1) | Ranked by what could hurt, across projects; every tile traces to rows, never a score with no contributors | ⚠️ |
| F-DIR-3 | Portfolio decision queue (Q2) | Same queue as the manager's, unfiltered; a director closing tickets is a signal the queue is broken, not a feature | ⚠️ |
| F-DIR-4 | Notifiable-incident escalation | Against a deadline someone owns (BR-I4). Occurred-at and reported-at never conflated (BR-I3). This is the director's alone | ❌ no clock exists |
| F-DIR-5 | External release | To client, regulator or board: what · to whom · by whom · when. A decision with an author, never a visibility setting. The four audience packs are cuts of one record — one derivation, four renderers (boardroom §2) | ❌ |
| F-DIR-6 | The incident spine | One URL per event, end to end, with the recurrence link. DecisionRecord already has the shape (app/lib/ledger.ts:15); it needs a live source | ❌ |
| F-DIR-7 | Integrity panel across projects (Q3) | The differentiator: it reports on the quality of the evidence, not the performance of the crew | ⚠️ |
| F-DIR-8 | Delivery honesty panel (Q5) | Undelivered tickets, inspections due vs submitted, last contact per device and per inspector — the last one needs identity | ⚠️ |
| F-DIR-9 | Recurrence across projects | The same finding on three sites is a control problem, not three tickets. Nothing but repeatOf models this today | ⚠️ |
| F-DIR-10 | Raw-media access as a separate, logged grant | A voice recording is a person's voice; a fix sequence is their movements through a shift. Transcripts and photos by default; raw audio and raw traces logged and separately granted (FM-BOUNDARY, CG-1) | ❌ |
5. Denied
Substituting for the manager's verification · altering any record — append only (BR-X2) · raising and closing the same finding · the parked pre-operational gates, which are granted to nobody.
6. Done means
The director opens one page and can answer *what could hurt us, what needs me, is the record defensible, and is the field even reaching us* — across every project, with every number tracing back to rows.
R. Their Rita
Every role has their own agent instance. Same person, same scope, no authority (PORTAL-ROLES §3.4).
- Is the Live Brief already built — the five questions, and
INTENT, the target drift is measured against (app/lib/brief.ts). The deck's agent slide has no equivalent of intent; the code is ahead of it. - Answers across the portfolio, because this principal's scope is the portfolio — which is why F-DIR-1 blocks her too.
- Never composes a number. Every figure traces to rows, or she says she has no basis.
- Cannot escalate or release. Both are the director's signature (F-DIR-4, F-DIR-5).
Never, in this instance or any other: mark coverage · sign · submit · close a ticket · assign an owner · release anything · supply a value no person or sensor produced. She reads with this person's scope claim and holds none of this person's grants.
7. Traceability
BR-I3/I4 · BR-X2/X5 · BR-S2 · FR-ROLE-3/4/14 · CG-1 · RD-1 · PT-3 · PORTAL-ROLES §6.6 · PERSONA §5–6