Intent · Every environmental obligation current and evidenced — zero reportable exceedances at Woodbine (UTS).

Operating tolerance: issues closed in ≤ 5 days · no repeat findings · every permit condition met.

← Documentsdocs/BRD-lifecycle-all-phases.md3,768 words

Business Requirements — the whole ESG project lifecycle

Status: draft for review. Date: 2026-08-04. Revision A. Written by Claude Opus 5 (Claude Code) at Pete's request: build out the BRD for every state and every phase of ESG.

This document does not replace BRD-field-processes.md. That document is the business case for the four field processes, and it remains authoritative for them. It covers one cell of an eight-cell grid. This document covers the other seven: the three phases that happen before a site is ever walked, the closeout that happens after, and the rules that bind all of them into one project.

Identifier families here are new and additive — BR-LC, BR-REG, BR-BID, BR-CST, BR-MOB, BR-CLO, BR-ST. Nothing in the existing BR-CA, BR-S, BR-AU, BR-I, BR-X, BR-U families is renumbered.

Read with FRD-lifecycle-all-phases.md (the functional half), PORTAL-ROLES.md (who may act) and PERSONA-environmental-director.md (who this is for).


1. Purpose and scope

1.1 What was missing

The requirement set as it stands describes a system that begins the day a site is first walked. It has no representation of how the work was won, what it was priced at, what was promised in order to win it, or whether the site was ever fit to be operated. It also has no representation of what survives handover.

Two consequences, and both are commercial rather than technical:

  • The promise and the record cannot be reconciled. An environmental commitment made to win a contract is the same obligation that is later inspected against. If those live in different systems, nobody can answer "you bid this on the basis of X — did you do X?", which is the question asked in every claim, every review and every renewal.
  • Past performance cannot price future work. The register accumulates exactly the data that would let a bid be priced from evidence rather than optimism, and no path exists to use it.

1.2 The eight-cell grid

Four processes across four operating phases. The shaded cell is the only one specified today.

BiddingCosting & planningOnboardingManaging
NCRhistory prices the bidremediation contingencytemplate + ownersspecified
Inspectioncadence → labourcadence × durationtemplate + inspectorspecified
Investigationincident history = risk premiumresponse capacityescalation pathpartly specified
Auditcertification commitmentsprogramme coststandard + schedulespecified, unbuilt

1.3 Scope of this revision

In scope. Phases 1, 2, 3 and 5; the project lifecycle state model; the obligation register as the spine across phases; the states of every aggregate.

Out of scope. The four field processes themselves (see the field BRD); the identity and authority model (see PORTAL-ROLES); commercial contract management beyond its environmental scope; anything that is not an environmental, sustainability or governance obligation.


2. Current state, stated honestly

No phase other than managing exists in any layer.

EvidenceFinding
packages/esg-projects/src/index.tsThe canonical Project is id · name · client · contractRef. There is no lifecycle state. A project comes into existence already being inspected
app/lib/projects.tsCarries a phase field, but it holds prose — "Corridor · tunnel and surface", "Weekly inspection" — a description of the work, not a state anything can branch on
Repository-wide searchBid, tender, budget, costing, estimate, procurement, mobilisation and onboarding vocabulary returns one incidental hit
app/lib/obligations.ts, app/lib/permits.tsRegisters exist and carry real derivation, but nothing binds an obligation to a project — applicability is absent
docs/A TSD is cited as authority by packages/esg-events-obligation (TSD 2.1, 2.1.1, 4.3) and by PORTAL-ROLES (TSD 2.4), and does not exist in this repository

Phases 1–3 are therefore not thin. They are absent, and this document specifies them from zero rather than describing something partly built.


3. Business objectives

Extending BO-1..BO-9 in the field BRD.

IDObjectiveMeasure of success
BO-10A project has a lifecycle, and every record knows which phase produced itAny obligation, cost line or ticket can be traced to the phase it originated in
BO-11What was promised to win the work is what is inspected againstEvery obligation on a live site traces to a bid commitment, a permit condition, or a stated later addition — with no orphans
BO-12A bid is priced from what comparable work actually cost, not from estimateBid packs cite measured history: NCRs per inspection, days-to-close, environmental delay
BO-13The environmental scope gates the programme as well as costing itPermit lead times and environmental windows are issued as dated constraints before the schedule is baselined
BO-14A site does not begin producing records until somebody accepted it was fit toEvery operating site carries a mobilisation sign-off naming a person and a date
BO-15Obligations that outlive construction survive handoverNo monitoring or restoration obligation is lost at practical completion
BO-16Every aggregate has an explicit, closed set of statesNo record is ever in an undefined or inferred state

BO-11 is the commercial heart of this document. The rest are supporting.


4. Stakeholders by phase

The field BRD's stakeholder table holds for phase 4. Phases 1–3 and 5 add parties who never appear on a site.

PhaseWho decidesWho is consultedWho is accountable
1 · BiddingBid/commercial leadEnvironmental director, planner, estimatorEnvironmental director for the environmental conditions attached
2 · Costing & planningCommercial lead + plannerEnvironmental director, specialist subconsultantsEnvironmental director for the budget and the dated constraints
3 · OnboardingProject managerEnvironmental manager, inspector, IT/platform adminEnvironmental director for the mobilisation sign-off
4 · ManagingEnvironmental managerInspector, supervisor, HSE leadEnvironmental director
5 · CloseoutProject managerEnvironmental director, regulator, clientEnvironmental director for surviving obligations

5. The lifecycle

5.1 The phases, and what each ends with

PhaseThe questionEnds with
1 · BiddingWhat would this bind us to, and can we carry it?Go / no-go, with environmental conditions attached
2 · Costing & planningWhat does the environmental scope cost, and what does it gate?A signed environmental budget + a list of dated constraints issued to the planner
3 · OnboardingIs this site actually fit to be operated?Mobilisation sign-off — this site may now produce records
4 · ManagingIs the record defensible, and is anything about to hurt me?A defensible record and a pack that survives challenge
5 · CloseoutWhat survives us leaving?A handover register of obligations that outlive the works

5.2 Cross-phase rules

IDBusiness rule
BR-LC-1A project has exactly one lifecycle state at any time, drawn from a closed set, and the state is a recorded fact rather than a derived guess
BR-LC-2Phase transitions are decisions, not schedule events. Each is an appended record naming the person, the date and the grounds
BR-LC-3A phase transition may be refused, and the refusal is recorded with its reason. A project that cannot mobilise must be visible as such
BR-LC-4Phases may be re-entered. A live project that wins a variation re-enters costing for that scope; re-entry never rewrites the prior phase's record
BR-LC-5A lost bid is a terminal state that is retained, not a deleted record. What we bid and did not win is the comparison set that prices the next bid
BR-LC-6Records created in one phase remain attributable to it forever. An obligation added at mobilisation must not be indistinguishable from one promised at bid
BR-LC-7No phase may be skipped silently. Operating a site with no mobilisation sign-off is permitted only as a recorded exception naming who accepted the risk

5.3 The register is the spine

IDBusiness rule
BR-REG-1An obligation is one object across the whole lifecycle. Identified at bid, priced at costing, applied at mobilisation, inspected at managing, and handed over or discharged at closeout — the same record throughout
BR-REG-2Every obligation carries its origin: bid commitment · permit condition · statutory requirement · client instruction · internally raised. Origin is never inferred
BR-REG-3An obligation must be applicable to a project to bind it. A register with no applicability model binds nothing and everything, which is the same as binding nothing
BR-REG-4An obligation promised at bid and not carried forward into the live project must be reportable as such. Silent disappearance is the failure BO-11 exists to prevent
BR-REG-5An obligation library may be reused across bids; a project's obligations are instances of library entries, not copies that drift
BR-REG-6Where an obligation is varied after award, the variation is appended with its authority. The original text remains readable

6. Phase 1 — Bidding

6.1 What the phase is for

To answer, before commitment: what would this contract oblige us to do, what would that cost, can we resource it, and what conditions must be attached to any bid we submit.

6.2 Business rules

IDBusiness rule
BR-BID-1A bid carries an environmental scope: the obligations, permits, approvals and monitoring programmes the contract would create
BR-BID-2The environmental scope is drawn from a library, not re-read from the specification by whoever is free that week
BR-BID-3A bid must state its environmental risk premium — the receptors, sensitivities, windows and ground conditions that make this site dearer than its area suggests
BR-BID-4A bid must be checked against inspector capacity already committed across the live portfolio. Winning work we cannot staff is a compliance failure with a lead time
BR-BID-5A bid must cite comparable measured history where comparable projects exist: NCRs per inspection, median days to close, regulator attention, environmental delay. Where none exists the bid says so rather than estimating silently
BR-BID-6The environmental director records a go / no-go with conditions. Conditions attach to the bid and survive into the project if it is won
BR-BID-7A bid is retained whether won or lost, with its outcome, because the comparison set is the asset (BR-LC-5)
BR-BID-8Bid material is commercially confidential and its visibility is narrower than the operating record's

6.3 Why this is worth building

The register accumulates the only dataset that can price environmental risk from evidence. A competitor without records must estimate. This is the phase where the discipline of every other phase is converted into commercial advantage, and it is the phase most likely to be dismissed as "not compliance".


7. Phase 2 — Costing, budgeting and planning

7.1 Two outputs, routinely conflated

The environmental scope does not only cost money; it gates the programme. Treating it as a cost line alone is the single most expensive mistake in this phase, because a missed environmental window is not recoverable with money.

7.2 Business rules — the cost line

IDBusiness rule
BR-CST-1The environmental budget is composed of stated lines: inspection labour (cadence × duration × sites), monitoring programmes and equipment, specialist subconsultants, permit fees, and remediation contingency
BR-CST-2Remediation contingency is priced from measured history where it exists (BR-BID-5), and the basis is recorded either way
BR-CST-3The environmental budget is signed by the environmental director. An unsigned budget is a proposal, and the project must be able to report that it is operating against one
BR-CST-4Budget consumed is reportable against budget signed, per project and per portfolio

7.3 Business rules — the constraints

IDBusiness rule
BR-CST-5Permit lead times are schedule constraints, not compliance items to be tracked once work starts. A permit that takes 90 days to issue constrains the construction sequence
BR-CST-6Environmental windows — in-water timing, migratory bird nesting, fish spawning, species-at-risk restrictions — are recorded as dated constraints with their authority
BR-CST-7Constraints are issued to the planner as a dated list before the schedule is baselined, and the issue is a recorded event
BR-CST-8Baseline monitoring that must run before works commence is identified in this phase, because after commencement it cannot be obtained at any price
BR-CST-9A constraint that is breached or waived must be recorded with the authority that permitted it. A window missed silently is the most expensive record in this system

8. Phase 3 — Onboarding and mobilisation

8.1 What the phase is for

To turn a won contract into a site that can produce defensible records. Its output is a readiness gate, and the gate is the point: a site producing records before it was fit to produce them produces bad ones, and nobody knows which ones.

8.2 Business rules

IDBusiness rule
BR-MOB-1A project must declare its kind — corridor · building · area site — because the kind decides which spatial model applies
BR-MOB-2A project must carry a boundary and its control areas, each with a category. Without them a finding cannot say where
BR-MOB-3A project must carry an asset register — the things with histories — or state that it has none
BR-MOB-4Applicability must be established: which obligations and permits bind this project (BR-REG-3), and obligations carried from the bid must be reconciled (BR-REG-4)
BR-MOB-5Permits must be recorded as in hand or applied for, and a site must not mobilise against an unissued permit without a recorded exception
BR-MOB-6An inspection template and a cadence must be assigned
BR-MOB-7A named inspector with a working device must be assigned. An actor string is not a person (see PORTAL-ROLES §3.2)
BR-MOB-8Baseline condition must be captured, or its absence recorded with the reason
BR-MOB-9Team and roles must be assigned, including who may sign off
BR-MOB-10The environmental director records a mobilisation sign-off: this site may now be operated. Every item above is either satisfied or explicitly waived, and a waiver names who accepted it
BR-MOB-11Mobilisation readiness is reportable while incomplete — the value is knowing what is outstanding, not only that the gate has passed

9. Phase 4 — Managing

Specified in BRD-field-processes.md §5, which remains authoritative. Two additions from the lifecycle view:

IDBusiness rule
BR-LC-8The operating record must be able to state, for any obligation, which phase it originated in and whether it was promised, permitted or later added (BR-REG-2)
BR-LC-9Dated constraints issued in phase 2 remain live through phase 4 and are reportable as forthcoming, met, or breached (BR-CST-9)

10. Phase 5 — Closeout and what survives

10.1 The problem

Environmental obligations routinely outlive the works: restoration monitoring for several seasons, warranty periods, records retention against a limitation period, and reporting that continues after demobilisation. Whether this is a fifth phase or the tail of the fourth was logged as open decision CG-6; this document treats it as a phase because it has a different owner, a different cadence and a different reader.

10.2 Business rules

IDBusiness rule
BR-CLO-1At practical completion every obligation must be discharged, transferred or carried forward — and each of the three is an explicit decision, not an expiry
BR-CLO-2Obligations carried forward form a handover register with a named owner beyond the project team
BR-CLO-3Monitoring that continues after demobilisation must retain a cadence, an owner and a reporting route
BR-CLO-4The records retention period is recorded per project against the applicable limitation period, and records are not disposable before it
BR-CLO-5A closeout report states what was promised, what was done, what was found and what survives — the phase-1 promise reconciled against the phase-4 record (BO-11)
BR-CLO-6A project in closeout is read-only for capture but must remain fully readable, because a challenge arrives after the team has gone

11. The state model

Every aggregate has a closed set of states (BO-16). Full transitions and guards are specified in FRD-lifecycle-all-phases.md §3; this is the business view.

AggregateStatesTerminal
Projectprospect → bidding → bid-submitted → won / lost → planning → mobilising → operating → closing → closedlost, closed
Biddrafting → scoped → conditioned → submitted → won / lost / withdrawnwon, lost, withdrawn
Environmental budgetdraft → proposed → signed → supersededsuperseded
Constraintidentified → issued → active → met / breached / waivedmet, breached, waived
Mobilisation gateopen → items-outstanding → signed / waived-in-part / refusedsigned, refused
Obligationidentified → applicable → active → met / overdue → discharged / transferred / carried-forwarddischarged, transferred
Permitrequired → applied → issued → active → expiring → expired / renewed / surrenderedexpired, surrendered
NCRopen → assigned → actioned → verified → closed (reopenable)closed
Inspectionscheduled → in-progress → signed → delivereddelivered
Auditscheduled → in-progress → findings-graded → concludedconcluded
Incidentreported → investigating → contained → closed → verifiedverified
Investigationopened → evidence-gathered → cause-determined → actions-raised → concludedconcluded
IDBusiness rule
BR-ST-1Every aggregate is in exactly one state from its closed set. There is no null, no unknown and no inferred state
BR-ST-2Every transition is an appended event naming actor, time and grounds. States are never edited in place
BR-ST-3A transition that a rule forbids must be refused with a stated reason, never silently ignored
BR-ST-4Terminal states are reachable only by a decision, never by the passage of time. An obligation does not become discharged because its date passed
BR-ST-5Where a state is derived for display (e.g. overdue, expiring), the derivation is stated and the underlying facts remain visible

12. Assumptions

IDAssumptionIf wrong
AS-10One project may re-enter costing for a variation without a new project recordVariations need their own aggregate
AS-11The obligation library is shared across bids within a tenantPer-project authoring; BR-REG-5 changes
AS-12Bid data is visible to a narrower audience than operating dataThe role model needs a commercial band
AS-13Closeout obligations remain in this system rather than transferring to an asset-management systemAn export contract is required

13. Dependencies

IDDependencyOwner
DP-10A decision on Project lifecycle state — widened aggregate, or a separate pre-award aggregate (CG-7)Architecture
DP-11The signed claim carries project singular (RD-1), so no portfolio-scoped phase view is expressibleArchitecture
DP-12A store the console can write to — every phase output here is a writeOperations
DP-13Identity and authority (S1/S2) — every phase gate is a signatureOperations
DP-14The TSD, which is cited by code and absent from the repositoryWhoever holds it
DP-15The applicable environmental windows and lead times for the operating regionEnvironmental director

14. Out of scope

Commercial bid pricing beyond environmental lines; procurement and subcontracting; general project scheduling; asset management after handover; health and safety except where an incident is both; carbon and sustainability reporting unless it is an obligation on the register.


15. Open decisions

IDQuestionOwner
CG-6Is post-construction monitoring a fifth phase or the tail of the fourth? (this document assumes a phase)Director / commercial
CG-7Does Project gain lifecycle state, or do phases 1–3 live in a separate pre-award aggregate?Architecture
CG-8Is the obligation library shared across bids or authored per project?Director / architecture
LC-1Does a lost bid retain its full environmental scope, or only its summary?Commercial
LC-2Who owns a carried-forward obligation once the project team demobilises?Director / operations
LC-3May a site operate against an applied-for-but-unissued permit, and who accepts that risk?Director / legal
LC-4Is the environmental budget a control (work stops) or a measure (variance reported)?Commercial

16. Traceability

ObjectiveRules
BO-10 lifecycleBR-LC-1..7, BR-ST-1..5
BO-11 promise = recordBR-REG-1..6, BR-BID-6, BR-MOB-4, BR-CLO-5
BO-12 priced from historyBR-BID-5, BR-CST-2, BR-LC-5
BO-13 scope gates programmeBR-CST-5..9
BO-14 fit to operateBR-MOB-1..11
BO-15 survives handoverBR-CLO-1..6
BO-16 explicit statesBR-ST-1..5, §11