Intent · Every environmental obligation current and evidenced — zero reportable exceedances at Woodbine (UTS).

Operating tolerance: issues closed in ≤ 5 days · no repeat findings · every permit condition met.

Sam Iyer · Field inspector / environmental tech

“What am I walking today, and did what I sent arrive?”

This surface: What authorises the work, and when each authority lapses.

Band · inspector
Cadence · Every shift
Employee
What the record ties to this person

The record says “M. Michaud”, not Sam Iyer: 0 of 0 tickets assigned to that string are open · 3 raised by them. A signature naming a role string identifies nobody.

May sign · may not

Attest a section — whole-section or item-by-item (+2 more) · Close a ticket they raised (+1 more). Printed, not enforced: nothing in this console checks a permission.

Module · Permits

Permit register

Every environmental permit held against the site — number, issuer, effective and expiry dates, and what it covers. The anchor every obligation traces back to. Sort by any column, filter by status, or search.

Permits
8
Held on this site
Expired
1
Past their expiry date
Expiring
3
Lapse within 60 days
Conditions
47
Obligations traced to permits
8 of 8
ESDP-2025-338
Endangered species dev. permit — habitat windowExpired
Vegetation clearing outside the breeding-bird window; monitoring and mitigation reporting.
Held by Env monitor · 5 conditions · effective Sep 1, 2025
MECP · SAROSpecies at riskWoodbine — south verge
Jun 30, 202618d overdue
NOISE-EXM-2026-14
Municipal noise by-law exemption — night worksExpiring
Extended-hours track work during scheduled rail possessions; community notification required.
Held by Site super · 3 conditions · effective Feb 1, 2026
City of TorontoNoiseWoodbine — track possession
Jul 20, 2026in 2d
WASTE-GEN-77120
Generator registration — non-hazardous wasteExpiring
Generation and off-site movement of construction & excavation waste; manifest retention.
Held by Logistics lead · 5 conditions · effective Nov 1, 2024
MECP · HWINWasteWoodbine — laydown
Jul 24, 2026in 6d
PTTW-6633-118
Permit To Take Water — construction dewateringExpiring
Dewatering of excavations up to 400,000 L/day, with discharge monitoring to the storm system.
Held by Site super · 7 conditions · effective May 15, 2025
MECP · PTTWWater takingWoodbine — cut & cover
Aug 31, 2026in 44d
TRCA-2025-0912
TRCA Permit — watercourse & sediment controlActive
Works within the regulated area; sediment fencing, erosion control and post-rainfall inspection.
Held by Env monitor · 6 conditions · effective Apr 1, 2025
TRCAWatercourseWoodbine — north crossing
Sep 30, 2026
ECA-8421-AKQR7
Environmental Compliance Approval — Air & NoiseActive
Crushing, screening and concrete batching; stationary plant emissions and site noise limits.
Held by Env manager · 9 conditions · effective Mar 1, 2024
MECP · EASRAir & noiseWoodbine — main compound
Feb 28, 2027
ROW-METX-4471
Metrolinx right-of-way environmental permitActive
Environmental controls for works within the rail corridor; dust, runoff and vibration limits.
Held by Env manager · 8 conditions · effective Jun 15, 2024
MetrolinxRight of wayWoodbine — corridor
Jun 14, 2027
SPILLS-EMP-004
Spill prevention & response plan (registered)Active
Fuel and hydraulic storage, spill kit manifests and reporting thresholds under O.Reg 675/98.
Held by HSE lead · 4 conditions · effective Jan 10, 2025
MECP · SpillsSpillsWoodbine — fuelling points
No expiryStanding registration

Conditions extracted from each permit become tracked obligations. Illustrative data · ONxpress CJV · Woodbine (UTS).

The surface above is the same for every role. `?role=` states who is looking and shapes what is emphasised; it filters nothing and withholds nothing, because there is no identity service, no session and no permission check in this console. A role banner over an unfiltered page is only honest while it says so.